One of the most frequent questions sent to our inbox is about the order completion time. It is understandable- each of you has deadlines to meet, so we will try to answer in general.
We should start with the fact that projects can be different as night and day. Deadlines depend on the number of ordered PCBs, the ammount of components which go into them, SMD assembly, THT assembly and various other factors.
Price evaluation time- from 24 hours to a week
Usually, pricing is done within 24 hours, unless there are many components to be estimated or if they require more „looking into”.
ASSEMBLY- from 1 day to 2 weeks
Time depends on the volume of PCBs and the size of the order. We encourage you to plan your order in advance. The earlier the order is placed the earlier we can book a deadline and manage your expecatations.
COMPILING COMPONENTS AND PCBs – 1 to 3 weeks
The most time consuming part is the compiling of electronic components for the order. We get varying ready dates from different wholesalers all over the world which increases the waiting time for the delivery of components. Normally it takes 1-2 weeks to gather all the components, but the harder the components are to find, the longer the ordering takes. It is a factor beyond our control, therefore if time is important to You, we suggest delivering the components by yourself.
The presented deadlines are only estimates resulting from experience. In order to find out the deadlines of a particular project, please send your questions to the following e-mail address: